Dubai Metro Gold Line: 42 km Route, 18 Stations and 2032 Opening


Deprecated: Using null as the key parameter for array_key_exists() is deprecated, use an empty string instead in /home/ayesha/paxitrack.com/wp-content/plugins/kadence-blocks-pro/includes/dynamic-content/class-kadence-blocks-pro-dynamic-content.php on line 1295
Asan TataAsan Tata— November 23, 2026
Join WhatsAppJoin Now

Dubai has approved its biggest transport project yet. The Dubai Metro Gold Line is a 42 kilometre, fully underground metro line with 18 stations. It will run from Al Ghubaiba in old Dubai to Jumeirah Golf Estates in the south, and it is planned to open on 9 September 2032.

Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the project on 22 April 2026. The Roads and Transport Authority (RTA) calls it Dubai’s largest sustainable transport project, at a cost of about AED 34 billion.

Quick Answer

The Dubai Metro Gold Line is a 42 km fully underground line with 18 stations, approved on 22 April 2026 at a cost of about AED 34 billion. It runs from Al Ghubaiba to Jumeirah Golf Estates, connects with the Red Line at two stations and the Green Line at one, and is planned to open on 9 September 2032. No station list and no fares have been published yet, so the 2032 date is a target, not a promise.

What Is the Dubai Metro Gold Line?

The Dubai Metro Gold Line is the fourth line of the Dubai Metro. It is 42 kilometres long and has 18 stations. It is the first Dubai Metro line built fully underground, at a depth of up to 40 metres. The Red and Green Lines run mostly on raised tracks, while the Blue Line mixes underground and raised sections.

The RTA says the Gold Line is Dubai’s largest sustainable transport project. The investment is about AED 34 billion. The line will serve 15 strategic locations and 1.5 million people, and support travel to 55 large development projects under construction now.

The Gold Line will expand the Dubai Metro network by 35 per cent. Today the network covers 120 kilometres, counting the Blue Line. With the Gold Line, it will reach 162 kilometres, and stations will rise from 67 to 85.

Gold Line Route: From Al Ghubaiba to Jumeirah Golf Estates

The Gold Line starts at Al Ghubaiba in old Dubai and ends at Jumeirah Golf Estates in the south. RTA has named 15 strategic locations on the route.

Part of the routeAreas served
Old DubaiAl Ghubaiba, Mina Rashid
Central DubaiCity Walk, Business Bay, Mohammed Bin Rashid City
South-central DubaiNad Al Sheba, Mohammed bin Rashid Gardens, Meydan
New DubaiAl Barsha South, Jumeirah Village Circle, Jumeirah Golf Estates

One point matters for readers. RTA has published the route and the 15 locations, but it has not published a list of station names or exact station spots. Some websites show a station list, but those lists are not official. Do not plan a home purchase or a daily commute around a station name until RTA confirms it.

Where the Gold Line Connects With Other Lines

The Gold Line links with the Red Line, the Green Line and Etihad Rail, the national railway.

ConnectionWhere it happens
Red LineBusiness Bay and Jumeirah Golf Estates
Green LineAl Ghubaiba
Etihad RailMeydan and Jumeirah Golf Estates

Business Bay is in the centre of the city, close to Downtown Dubai. Jumeirah Golf Estates is at the southern end. From there, passengers can change to the Red Line and travel towards Dubai Marina and Jebel Ali.

The Green Line link at Al Ghubaiba connects the Gold Line to Deira and the old city. The Etihad Rail links at Meydan and Jumeirah Golf Estates connect Dubai’s metro to the national rail network, which already runs freight trains across the UAE. Passenger trains are planned.

Gold Line Timeline: Tender, Construction and Opening Date

The project will take about six years from approval to opening. RTA has set out the main steps.

StepWhen
Project approved22 April 2026
Tender issued2026
Contract awarded2027
Construction startsAfter the contract award
Planned opening9 September 2032

The tender stage is under way in 2026, and six contractor groups had sent in prequalification papers by October 2026, according to trade press reports. The main contract is due to be awarded in 2027, and building will then begin in earnest.

The opening date is 9 September 2032. Dubai Metro lines open on 9 September: the Red Line in 2009, the Green Line in 2011, and the Blue Line is due in 2029. The Gold Line would open on the same date in 2032, the 23rd anniversary of the Metro. RTA says it will be built 30 per cent faster than the Blue Line, using the latest tunnel boring machines.

Important Information

The 9 September 2032 opening is a target date set at approval, not a guaranteed date. Large metro projects can face delays. RTA has not published a station list or fares yet. Treat every date in this guide as planned until RTA confirms it closer to opening.

How the Gold Line Compares With the Blue Line

The Blue Line is already under construction, while the Gold Line is still at the tender stage. The two lines do different jobs.

FactBlue LineGold Line
Length30 km42 km
Stations1418
CostAbout AED 20.5 billionAbout AED 34 billion
Underground or raisedMixedFully underground
Approved24 November 202322 April 2026
Planned opening9 September 20299 September 2032

On 22 November 2026, Sheikh Hamdan bin Mohammed reviewed progress at the Blue Line worksite in Dubai Festival City. RTA said the project was 29 per cent complete, with tunnel digging 55 per cent done. The new Blue Line trains were also shown for the first time.

The Gold Line is bigger and more costly: 12 kilometres longer, four more stations, and fully underground, which makes it harder to build. It serves the centre and south of the city, while the Blue Line serves the east, including Mirdif, International City and Dubai Creek Harbour.

What the Gold Line Means for Commuters

The line will serve over 1.5 million people by 2040, and RTA expects daily passenger numbers to reach 465,000 beyond 2040. The Metro already carries about one million people a day on average.

The line will also ease pressure on the Red Line. RTA says it will cut crowding on the Red Line between BurJuman and ONPASSIVE stations by 23 per cent. That stretch is one of the busiest parts of the network at rush hour, as many workers travel from the south of the city to offices in the centre. The Gold Line gives them a second route.

The line should take cars off the road too. RTA says it will cut over 40 million road journeys a year. That should improve traffic flow on busy roads such as Sheikh Zayed Road and Al Khail Road, and cut fuel use and carbon emissions. It is part of the Dubai 2040 Urban Master Plan.

The line may also raise property values near its stations. RTA says property near metro stations could rise in value by up to 20 per cent. But this is a forecast, not a fact, and no station list exists yet.

Gold Line Fares and Tickets: What We Know So Far

RTA has not announced Gold Line fares. No ticket prices exist yet, and fares will be confirmed closer to 2032. Anyone who quotes a Gold Line fare today is guessing.

What we do know is how the rest of the Metro works. Dubai Metro uses the nol card system. Passengers tap a nol card at the gate and the fare is taken from the card balance. The same card works on the Metro, buses, trams and marine transport. The Gold Line will very likely use the same system. The Metro also has Silver Class and Gold Class travel, and the new Blue Line trains will have both. The Gold Line trains will probably follow the same pattern, but RTA has not shown their design yet.

Pro Tip

If you are thinking of renting or buying near the Gold Line route, wait for RTA to publish the official station list before you pay a premium for a “metro station” location. Until then, use the 15 named locations as a rough guide only, and check rta.ae for updates.

What Is Not Decided Yet

Much about the Gold Line is still open, so readers should know what is missing.

No official station list

RTA has named 15 locations, not 18 station names. The exact spot of each station is not public, and station names often change during design. Some lists online are guesses.

No fares

No fare has been set. Fares for new lines are usually announced near opening. The nol card system will almost certainly apply, but the price of a trip is unknown.

No construction start date

The tender is under way in 2026 and the contract award is due in 2027. Building will start after that. No firm start date has been announced, and the 9 September 2032 opening is a target, not a promise. Big underground projects can run late, though the Blue Line is on track for 2029 so far, which is a good sign.

Why the Gold Line Matters for Dubai’s Future

The Gold Line fits into a bigger plan. Dubai wants to double the size of its economy by 2033 under the Dubai Economic Agenda, known as D33. Good transport is part of that plan: it helps workers reach jobs and businesses in new districts grow.

RTA says the Gold Line will deliver a 430 per cent cumulative economic return over 20 years of operation, from savings in time and fuel, and from fewer road accidents and lower carbon emissions. It is a forecast by the authority, not a measured result. But it shows how the government sees the project: as an investment, not just a cost.

The line also supports the Dubai 2040 Urban Master Plan, which aims to make Dubai a city where people can live, work and travel without long car trips. The Gold Line links old Dubai with new districts in the south, connecting homes, offices, schools and shops along one underground route. In a few years, a person living in Jumeirah Village Circle or Al Barsha South may be able to take the Metro to Business Bay or Al Ghubaiba without a car. That is the promise.

Frequently Asked Questions

When will the Dubai Metro Gold Line open?

The planned opening date is 9 September 2032. That is the target RTA set at approval in April 2026. It is not guaranteed, so check RTA updates closer to the time.

How long is the Dubai Metro Gold Line and how many stations will it have?

The line is 42 kilometres long and will have 18 stations. It is Dubai’s first fully underground metro line, running at a depth of up to 40 metres.

Where does the Gold Line start and end?

It starts at Al Ghubaiba in old Dubai and ends at Jumeirah Golf Estates in the south. It passes through Mina Rashid, City Walk, Business Bay, Mohammed Bin Rashid City, Nad Al Sheba, Meydan, Al Barsha South and Jumeirah Village Circle.

Will the Gold Line connect with the Red and Green Lines?

Yes. It connects with the Red Line at Business Bay and Jumeirah Golf Estates, and with the Green Line at Al Ghubaiba. It also links with Etihad Rail at Meydan and Jumeirah Golf Estates.

What are the Gold Line fares?

No fares have been announced. RTA will confirm fares closer to opening. The rest of the Dubai Metro uses the nol card system, and the Gold Line is expected to use the same system.

Disclaimer: This article is for general information only. Project dates, station names and fares can change. Always check the Roads and Transport Authority website at rta.ae for the latest official updates before making travel or property decisions based on the Gold Line.

Last Updated: 23 November 2026